The HARP DPC Project comprises:
(a) design, construction, testing and commissioning of the works;
(b) planned and corrective maintenance, including lifecycle maintenance, of the assets following the completion of each section of the tunnel;
(c) the project management of these activities; and
(d) financing of the activities
The works and services for delivering the HARP DPC Project includes (but not limited to):
(a) The coordination of all design, construction, commissioning of works, implementation, and project management at all sites
(b) management of limiting environmental impact to local communities
(c) securing land and property rights
(d) obtaining and complying with all consents (including s.106 Agreements)
(e) compliance with all requirements with respect to biodiversity net gain
(f) design, construction, commissioning, implementation, testing & inspection of the works
(g) provision of all utilities and services necessary for the permanent operation of the new aqueduct, including activation any associated connection fees
(h) surveys, monitoring, and instrumentation works and services
(i) studies, investigations, and assessments
(j) reinstatement of all utilities, highways, footpaths, hardstanding and other items outside of the worksite that are damaged or temporarily modified during construction of the works
(k) engagement with stakeholders, local communities and third parties impacted by the HARP DPC Project (with listed exceptions) including complaints resolution
(l) provision of workforce occupational health services and well-being programmes
(m) ancillary activities necessary to ensure that the works and services are carried out in accordance with good industry practice
(n) protection and maintenance of the works through construction, testing and commissioning periods
(o) provision of as-built construction records, operation and maintenance documentation and other documentation for the HARP DPC Project
(p) provision of warranties and collateral warranties for plant and materials
(q) provision of temporary works to deliver the HARP DPC Project
(r) undertaking acceptance tests
(s) provision of all elements required for operational and maintenance access
(t) securing deeds of easement and rights of access along the entire length of the new HA tunnelled sections
(u) monitoring the impact of the works on private water supplies and arranging the provision of alternative water supplies where required
(v) provision of all other required works, services and activities required for specified operating techniques, parameters and restraints and water quality standards.