II.1)
Scope of the procurement
PRO004337-Works-Contract-Haweswater Aqueduct Resilience Programme
Reference number:
PRO004337
45000000
-
Construction work
Works
II.1.4)
Short description
United Utilities Water Limited (UU) proposes to deliver a scheme titled Haweswater Aqueduct Resilience Programme (HARP DPC Project) via Ofwat’s Direct Procurement for Customers (DPC) approach, engaging a Competitively Appointed Provider (CAP) to design, build, finance and maintain this major water resilience supply project.
The HARP DPC Project comprises the replacement of 6 tunnel sections of the existing Haweswater Aqueduct (HA), connections to existing multiline siphons between the tunnel sections and associated facilities. It also includes the commissioning and ongoing maintenance of those works for a period of approximately 25 years after completion.
Due to the complexity and profile of the HARP DPC Project, the precise detail of the underlying technical regime remains in development as at the date of this contract notice.
II.1.5)
Estimated total value
Value excluding VAT: 1750000000.00
GBP
II.1.6)
Information about lots
This contract is divided into lots:
no
II.2.2)
Additional CPV code(s)
43123000
-
Tunnelling machinery
43320000
-
Construction equipment
45221000
-
Construction work for bridges and tunnels, shafts and subways
45221200
-
Construction work for tunnels, shafts and subways
45221240
-
Construction work for tunnels
45221247
-
Tunnelling works
45231300
-
Construction work for water and sewage pipelines
45233000
-
Construction, foundation and surface works for highways, roads
45350000
-
Mechanical installations
50000000
-
Repair and maintenance services
63712320
-
Tunnel operation services
65100000
-
Water distribution and related services
65320000
-
Operation of electrical installations
66100000
-
Banking and investment services
66122000
-
Corporate finance and venture capital services
71000000
-
Architectural, construction, engineering and inspection services
71242000
-
Project and design preparation, estimation of costs
71322000
-
Engineering design services for the construction of civil engineering works
71500000
-
Construction-related services
71540000
-
Construction management services
71541000
-
Construction project management services
II.2.3)
Place of performance
NUTS code:
UKD -
NORTH WEST (ENGLAND)
II.2.4)
Description of the procurement
Works and services for delivering the HARP DPC Project are set out in the ‘additional information’ section.
Project agreement - The CAP will be appointed under a bespoke project agreement with UU, the term of the project agreement will be 25 years, plus a construction period. Further details are included in the project agreement.
Structure of the CAP - The tender process is designed to accommodate the participation of multi-party consortia, alongside other participants. Further details are included in the tender documents.
Independent Technical Advisor - Assurance for UU and customers under the project agreement will be provided by an Independent Technical Advisor (ITA) and Approved Assurer (AA). The ITA and AA will be appointed through a separate procurement process.
Bid costs - UU will pay a contribution to the tender process costs incurred by each of the unsuccessful bidders, terms of where this is due are included in the tender documents. Please note that the proposed payment of a contribution to the costs of an unsuccessful bidder is included in this tender process in recognition of the unique nature of the HARP DPC Project. It is not intended to set a precedent for future UU (or any other DPC) tender processes.
Planning - Planning submissions have been made by UU for the whole of the HARP DPC Project and UU currently anticipates that the outcome for each planning determination will achieve a consent from the relevant local planning authority prior to the submission of Final Tenders by the bidder however, it should be noted that the works on all six initial tunnel sections remain subject to planning determinations and the actual timing of receipt of these is beyond the direct control of UU. Whilst not currently anticipated, the failure of the planning determinations to grant the necessary consents (as sought by UU), or a significant delay to the planning determination, could make it impossible or not feasible to carry out and complete the works on a tunnel section. In those circumstances, UU may elect to remove one or more of the initial six tunnel sections from the scope of the HARP DPC Project, but reserves the right to continue with the procurement process on the basis of the reduced scope. This would have the effect of reducing both the scale and the value of the HARP DPC Project. Any such reduction would be confirmed to the short-listed bidders prior to the submission of final tenders. Further details are included in the tender documents. Please note that the questions in both the Pre-Qualification Questionnaire (PQQ) and the Invitation to Negotiate (ITN) are designed to be equally applicable (in terms of, respectively, setting appropriate pre-qualification requirements and identifying the most economically advantageous tender) where the scope of the HARP DPC Project is reduced in this way. UU does not, therefore, anticipate that the removal of any one or more of the tunnel section(s) from the scope would necessitate the re-running of the PQQ stage or any material changes to the submission requirements and evaluation criteria in the ITN.
Access to documents - Interested parties will be able to access the suite of tender documents on the electronic tendering portal (EU Supply) including;
PQQ and associated appendices
ITN and associated appendices and forms
Project agreement and schedules
Other supporting documents
UU standards and specification will be held on the UU Data Room, interested parties contact UU via the messaging tool on EU Supply in order to be granted access to view these documents.
Further information regarding the Ofwat methodology for DPC and HARP's designation as a DPC project can be viewed via the following links.
https://www.ofwat.gov.uk/wp-content/uploads/2017/12/Appendix-9-Direct-procurement-FM.pdf
https://www.ofwat.gov.uk/publication/direct-procurement-for-customers-project-designation-direction-issued-to-united-utilities-harp-scheme
Price is not the only award criterion and all criteria are stated only in the procurement documents
Value excluding VAT: 1750000000.00
GBP
II.2.7)
Duration of the contract, framework agreement or dynamic purchasing system
Duration in months:
400
This contract is subject to renewal:
no
II.2.9)
Information about the limits on the number of candidates to be invited
Envisaged number of candidates:
3
Objective criteria for choosing the limited number of candidates:
UU will be utilising the negotiated procedure with prior call for competition and intends to award the entire scope of the HARP DPC Project to a single CAP.
In order to appoint a CAP, UU will run a procurement process made up of a series of stages. As part of the PQQ UU will set selection criteria which will be used to determine a bidder’s suitability to be shortlisted to the next stage of the procurement (the ITN).
UU intends to issue the ITN to three applicants (selected on the basis of the highest scores from the PQQ stage). The applicant with the fourth highest score will be held as a reserve bidder for thirty days (or such period extended at UU’s discretion) from the formal issue of the ITN to the applicants successfully shortlisted. The reserve bidder will be added to the shortlist in the event one of the top three highest scoring shortlisted bidders drops out within the thirty day period (or longer, as applicable).
II.2.10)
Information about variants
Variants will be accepted:
no
II.2.11)
Information about options
Options:
yes
Description of options:
The parties (UU and CAP) may agree (in their absolute discretion) to extend the project term (by up to 10% of the project term) by agreeing to amend the expiry date. Such agreement shall be in writing, and include any changes to the project agreement to account for the extension as agreed by the parties and may also be subject to Ofwat's prior approval.
II.2.13)
Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
no
II.2.14)
Additional information
Disclaimer - This notice shall not have contractual effect between UU and any other person. The tender process that is launched by this notice is subject to the rights of UU as set out in the tender documents. Without limiting that, UU reserves the right not to enter into the project agreement, or any other contract or arrangement, pursuant to this tender process or at all.