The UK Atomic Energy Authority has a requirement for the relocation of a number of Transformers at its site at Culham Campus, Nr Abingdon, Oxfordshire. This involves lifting 10 transformers out though the roof of one building and repeating the process at the new building. Full details of the requirement are contained in the Invitation to Tender which is available from the link in this notice.
Works
17/12/2026 12:00:00
45232220-0 Substation construction work
45232221-7 Transformer substation
31170000-8 Transformers
31171000-5 Liquid dielectric transformers
31174000-6 Power supply transformers
51111300-6 Installation services of transformers
UK Atomic Energy Authority
Culham Science Centre
OX14 3DB
Oxfordshire
United Kingdom
View profile
https://www.gov.uk/government/organisations/uk-atomic-energy-authority
| Notice | Date of dispatch |
|---|---|
| Tender Notice (FTS (PA23)) | 12/11/2026 17:33 |