The removal of the existing mechanical services and the installation of the new gas fired boilers,flue system, pressurisation unit, boiler pumps, hot water calorifier water, BMS and controls, steel pipework, copper pipework, fittings, electrical works, builders work and asbestos removal. The work will be done in term time while the school is operational therefore the contractor will be required to collect and use a mobile boiler unit (provided by Kirklees) to maintain heating and hot water during the works.
20/01/2025 13:00:00
45331110-0 Boiler installation work
42160000-8 Boiler installations
45350000-5 Mechanical installations
45351000-2 Mechanical engineering installation works
71333000-1 Mechanical engineering services
71334000-8 Mechanical and electrical engineering services
Notice | Date of dispatch |
---|---|
Awarded Contract (Contracts Finder) | 04/02/2025 12:11 |