This contract relates to the construction of a 45m long gabion wall. The works briefly comprise site clearance, excavation of existing earthwork to install the gabion wall and associated back of wall drainage, disposal of material off site, placement of engineered fill behind the gabion wall, and verge widening / carriageway re-surfacing as required.
2024-03-06 12:00:00
45233130-9 [46721]
45233229-0 [46743]
45200000-9 [46402]
The North Yorkshire Council
County Hall, Racecourse Lane,
DL7 8AD
Northallerton
[GB]
[ViewProfile]
| [Notice] | [DispatchDate] |
|---|---|
| [CF02LiveOpportunity] ([ContractsFinderV2]) | 2024-02-08 11:07 |
| [CF03Award] ([ContractsFinderV2]) | 2024-09-24 10:44 |