Please find enclosed opportunity for resurfacing works on Fielders Way, Edlington.
Please note, works are to take place as follows:
Day 1 Sunday Evening - 29/01/2023 - 17:00 - 06:00
Section A
Replace existing gully / manhole cover and frames and adjust ironwork levels.
Plane carriageway 40mm deep.
Tanker applied bond coat
Lay SMA 10 SURF 40/60 40mm thick.
Day 2 Monday - 30/01/2023 - 08:00 - 18:00
Section B
Replace existing Gully manhole covers and frames and adjust ironwork levels.
Plane carriageway 40mm deep.
Tanker applied bondcoat
Lay SMA 10 SURF 40/60 40mm thick.
THE GENERAL ARRANGEMENT DRAWING STATES PLANING OUT 60MM. THIS IS INCORRECT. PLEASE PRICE AS PER THE BOQ
Tender return date is 18.01.23 at noon.