This procurement is for the replacement of the boardwalk decking at Castleford Bridge. Works are to commence in Spring 2023 with a Contract Period of seven weeks. This will include an initial 4 weeks to carry out design and obtain design approval followed by 3 weeks on site work. The starting date on site will also be dictated by a 2-month period to obtain consent from the Environment Agency.
25/11/2022 12:00:00
45221113-7 Footbridge construction work
Wakefield Council
Wakefield One, Burton street
WF1 2EB
Wakefield
United Kingdom
View profile