I would like to invite you to provide a tender based on the attached BOQ to carry out the above scheme as identified in the design, specifications and drawings that accompany this tender.
Please note, given the road closure and traffic management required to carry out this scheme the successful contractor must be able to commence work on Sunday 2nd October.
Works are to take place as follows:
Sunday 2nd October - Phase 1 - Plane, Geo, Base - 08:00 - 18:00
Monday 3rd October & Tuesday 4th October - Phase 2 - Plane, Geo, Base - 09:30 - 15:30
Sunday 9th October - Surface Phase 1 & Phase 2 - 08:00 - 18:00
Return date is noon on 01/09/2022