Ascot Avenue & Aintree Avenue, Cantley

The quote/tender has ended, you cannot answer the invitation.

Enclosed is an opportunity for works at Ascot Avenue/Aintree Avenue. 

Works to take place as follows:

Please note, given the road closure and traffic management required to carry out this scheme the successful contractor must be able to commence work on Monday 10th October - Friday 14th October. Works to take place between 09:00 - 15:30 daily.

 Works are to take place as follows:

 Monday 10th October - Plane/Geo/Base Phase 1

 Tuesday 11th October - Plane/Geo/Base Phase 2

 Wednesday 12th October - Surfacing Phase 1

 Thursday 13th October - Surfacing Phase 2

Return date is noon on the 1st September.