Enclosed is an opportunity for works at Ascot Avenue/Aintree Avenue.
Works to take place as follows:
Please note, given the road closure and traffic management required to carry out this scheme the successful contractor must be able to commence work on Monday 10th October - Friday 14th October. Works to take place between 09:00 - 15:30 daily.
Works are to take place as follows:
Monday 10th October - Plane/Geo/Base Phase 1
Tuesday 11th October - Plane/Geo/Base Phase 2
Wednesday 12th October - Surfacing Phase 1
Thursday 13th October - Surfacing Phase 2
Return date is noon on the 1st September.