The 500KvA generator for the CMD Building requires an upgrade to 700KvA The new generator will need to be installed in the existing location in the compound behind CMD and all electrical connections to the existing generator to be disconnected and reconnected to the new generator. On completion of the installation a load bank test is required to test 100% loading of the generator and confirmation that the auto changeover controls work correctly. The old generator is to remain on site at FHQ.